PROJECT NAME:
PROJECT NAME:
Objectives & Site Considerations:
At the start of the COVID-19 pandemic, The client’s daughter and her family moved back into their home with them in the Snowy Mountains. With three generations now living under one roof, working from home, and home-schooling their grandchildren, they wanted some relief from increasing electricity costs.
The original ground-mounted solar framing footings needed to be changed after it was determined that the soil type was too rocky. A concrete slab was then determined to be the most suitable option.
Load Analysis:
Average summer demand: 50kWh
Average winter demand: 65kWh
System Design:
Project Outcome:
They have since expanded the solar and given us feedback that they loved our work and that we were easy to deal with.
After running their Murray Cod Aquaculture operation from expensive diesel generators for years, Coobool Downs wanted an alternative.
A huge effort by our team to salvage this system and provide a safe and working off-grid system for the Farrowing Property.