PROJECT NAME:
Objective:
Powering multiple buildings, both on and off grid, for Sea Dragon Lodge Luxury Eco Accommodation
2014 Install (Autonomy): While the site had grid power available, it wasn’t adequate for the power needed by the new eco villas. The grid will provide backup power for low battery SOC% or high power demand.
2018 Installs (Autonomy Upgrade, and Complete System): With more villas and a new office built, the original system needed expansion.
A separate off grid system was also needed for the new staff quarters, a cottage, and a 3 bedroom villa.
Site Considerations:
Cable sizes needed to be carefully planned for both the 2014 and 2018 installations as the buildings were, in some cases, quite a distance apart.
Load Analysis:
2014 Install
2018 Off-Grid Install
System Design:
2014 Install
2018 Off Grid Install
Project Outcome:
“The boys did a nice job on the installs”
-Steve
To check out the systems for yourself, book a few nights in their stunning oceanview villas at https://seadragonlodge.com.au/